Photo by Hank Lohmeyer
Heavy equipment arrived in the small neighborhood atop Cory Bluff last Friday evening and began 24-hour operations to get the North Delta Irrigation tunnel project back on track.
Crews working to install irrigation pipeline in a partially collapsed tunnel under Cory Bench ran into unexpected problems last week.

A shackle and cable assembly attached to the four-foot-diameter pipeline which enabled equipment to pull it through the tunnel bore failed during operations last Wednesday.